Glyncollen and Newton Project Timelines

Details of the project milestones, from approval to completion.

Newton Primary School

 

December 2013

  • Approval granted by Welsh Government
  • Planning approval granted
  • Works commence

January 2014 - August 2014

  • Ground works
  • Buildings constructed
  • Demountables demolished
  • External works and landscaping

September 2014

  • Classrooms occupied and pupils enjoy new learning environment
  • Project completion
     

 

Glyncollen Primary School

 

December 2013

  • Approval granted by Welsh Government
  • Planning approval granted

February 2014 - August 2014

  • Works commence
  • Demountables demolished
  • Ground works
  • Buildings constructed
  • External works and landscaping

September 2014

  • Classrooms occupied and pupils enjoy new learning environment
  • Project completion